Brick Center Substation

Gill Ranch Storage Substation

Ryan Dam GSU Transformer Replacement

 

The Ryan Dam is located near Great Falls, MT on the Missouri River.  IEC was contracted with PPL Montana (PPL) for this design-build project.

For this generator step-up project, IEC was responsible for replacing eleven (11) single-phase transformers with two (2) 50 MVA transformers.  Other major components of work for this project included: new 15kV switchgear, with new feeder bays and a new control system, new 100kV circuit switchers, HVAC and a new fire annunciation system.

IEC began construction on this project in March 2007 and was completed on-time in May 2008.